Q:

04.036 Does the LA have a deadline by which to amend a plan where a CYP is transferring between phases of education?

Noddy 'no-nonsense' Guide

Noddy 'no-nonsense' Guide
Authors: David Wolfe QC, Leon Glenister
03 Mar 2024

A: SenseCheck

  • 1 Yes
  • 0 No
  • 0 Other

Sort

  • 03 Mar 2024
  • Yes

    Complex

    A transfer between phases of education is early years education to school, infant school to junior school, primary school to middle school or secondary school, middle school to secondary school or secondary school to a post 16 institution: Regs2014 r2(1). In such a case the LA must review and amend (where necessary) the CYP’s EHCP before 15 February in the calendar year of the transfer (or 31 March where transfer is from secondary school to post-16 institution): Regs2014 r18(1)